Sunday, February 27, 2011

Stop in the Name of the Law!

Everything was rockin’ along last week. 

The masons continued their work on the fireplaces,

P1140782

the low voltage guys got things wound up for the inspection,

P1140805

the framers continued putting up the fascia,

P1140767

Builder Gary’s faithful sidekicks boxed in the gas fireplace in the living room,

P1140774

the roofers came and put down a  layer of felt paper,

P1140776

and the guys from Wolf Lightning protection brought out scads of thick copper rope:

P1140792

which they fastened along the ridge poles,

P1140796

with lightning rods going out through the roof.

P1140800

They pulled the wire (rope) down the end walls and fastened along the eaves,

P1140794

down the walls of the house,

P1140802

and out at ground level

P1140807

like a little pig tail in to the yard,

P1140789

where it will be tied into a buried loop of copper wire.

Take that, lightning!

Anyway, this was the scene when the electrical inspector came out to inspect the rough in electrical and low voltage.  This was the scene that he tried to alter by dropping a stop work order on us.

I was off at the flower show and came back just as the dust cloud was dissipating.

Apparently, the electrical inspector wasn’t aware that the electrician had pulled a low voltage permit.  Then when he saw the lightning protection going on, he demanded to see the Georgia license of the lightning guy.  The lightning guy does work all over the world and has an international license.  Therefore he doesn’t need a Georgia license, right?

Not according to the electrical inspector.  The inspector’s supervisor told the lightning guy that the international license was fine, but at this point the inspector was on a roll.   He dropped a stop work order on the build and threatened to haul the lightning guy off to jail.

Gary talked him into letting the masons and the framers continue their work and just stopping the lightning protection and any further low or high voltage wiring.

So there we stood at 2 PM on a beautiful sunny Friday needing to finish the lightning protection.  I wanted them to keep working.  Builder Gary didn’t want to have to spend the evening collecting bail for the lightning guy.

I asked to see the inspector’s card.  Not much information there:

P1140779

The flip side didn’t even show which inspector came out,

P1140780

But my money’s on ol’ Colin.  Just sayin’….

One nugget of information that the card did reveal was the name and cell number of the supervisor inspector.  I called him.  Builder Gary ran away.  He doesn’t trust me to mind my manners.  I merely put on my blonde wig and asked the supervisor to explain what had happened.  He told me that it was a mistake. He was lifting the stop work order and we could keep on stringing copper cable.

Whew!   Back to work they went and finished up the lightning job.

Then on Saturday, the plumbers came out with little jackets.  You see the rough in plumbing failed its inspection, because the recirculating hot water pipes didn’t dress properly.  Apparently it was a black tie affair and a black jacket was de rigueur.

P1140813

So, they came back down and dressed all the recirculating pipes according to code.   A dress code for plumbing pipes. Who knew?

I can’t wait for more fun with inspectors next week.

And just in case, does anyone know the name of a reliable bail bondman?

Wednesday, February 23, 2011

Putting a Damper on Things

Is it an oxymoron to say that I was excited to have a damper put on something?

P1140727

The brickyard was out of dampers and left them off the order when they delivered the bricks.  So, yesterday no brick work was done.  The dampers arrived today and the masons got right back to work.

 

P1140747

Have you ever wondered why dampers have adjustments?  I mean, after you open the damper and build a fire, are you really going to say, “Gee I think I’ll reach up there and open the damper a little more?” 

Maybe it’s an energy saving measure so that you can close it down a bit when the fire dies down.  But I still wouldn’t want to reach up through the smoke and grab onto a piece of cast iron that has been above the fire for an hour or two.  Would you?

P1140750

Anyway, I think there is a lot of appeal to being a mason. You get to play with building blocks, and with mud.

P1140749

Big, glorious, gloppy wheel barrows full of mud.

P1140728

And then you get to be all precise and get everything all trimmed up and level so that nobody knows what a mess you made.

P1140758

Meanwhile not to be outdone by the mason’s neatness, here’s Bill:

P1140752

Bill has been hanging around for about a week. 

He’s been hanging around the rafters, the ceiling joists, the floor joists, and everywhere else.  And while he hangs there, he pulls cable.

P1140754

Miles and miles of cable.

P1140753

Boxes of every color cable imaginable.

P1140756

There is so much cable here you can hardly swing a CAT (5 or 6).

P1140757

But see how it is all so neatly labeled? Soon it will all go into the home automation panel and each labeled cable will go just where it needs to for the alarm or the audio system or the computer network.

Meanwhile out front, the framers were back doing a little tidying themselves.  Check out the before:

P1140742

and after:

P1140736

They were putting up the cornice boards and the fascia.

 

P1140738

Everything was getting trimmed out and ready for the roofer.

P1140739

And speaking of trim,

P1140761

Builder Gary nailed up a few pieces of trim around the window and the corner so we could get a sense of scale.  The corner board looks kind of bulky on this short wall, but…

P1140760

taking in more of the house, it doesn’t seem so bad.

image

 

I guess that’s how it is supposed to look.

Monday, February 21, 2011

Monday Madness

P1140661

Things were really popping today! When I got down to the new house to do the electrical walk through, the plumbing inspector had already been there, and the water meter guys were getting ready to tear things up.

P1140663

Then I walked in and found the gas fireplace sitting in the middle of the living room.

P1140664

Not to be outdone, Jason the Mason and his crew were well on their way to building the firebox for the family room fireplace.

P1140645

We walked through checking on canned lights in the kitchen,

P1140648

outlets on the porch, and all the rest.

P1140666

Meanwhile back at the street, they had dug up the road.

P1140672

They found the water main, and attached…

P1140676

this nifty little gizmo to tie us into the city water.

P1140673

Then they put the “magic bullet” down in the trench at the curb and let it work its way like a pneumatic robotic mole under the street to the waiting water main.

P1140679

While that was working, the guys got to work measuring out the 1” copper pipe that would connect the water meter to the main.

P1140684

When the trusty metal mole came through, they taped up the end of the copper pipe …

P1140685

and fed it through the tunnel to the hole in the street.

P1140687

A little coaxing, some hand tightening,

P1140693

and a little wrench work later, we had a fountain

P1140697

arcing across the driveway.

Satisfied that the first bit worked, they got to work on the business end:

P1140688

They had to put this water meter in,

P1140698

leaving some pipe for us to attach to,

P1140702

and then encase the whole deal in the cast iron casket:

P1140709

Soon enough it looked like a water meter.

P1140723

They didn’t exactly put it where I had my stake, but hopefully we’ll get the gas people to work around it.

Meanwhile, back in the bat cave,

P1140669

The gas fireplace installers were smoking along.

P1140671

What light above yon window shines?

Yea, though it shines like the moon, methinks it is instead the hole for the vent pipe.

P1140722

They got the vent out where I thought it would be the least conspicuous, and they installed the bling:

P1140677

I think we can paint it to match the siding, and it will be very low key.

P1140716

And this is how it is placed in the room as you enter from the front foyer.

P1140714

Meanwhile in the family room, Jason wanted to demonstrate the arch he plans to put on the fireplace. He was just about finished with the firebox and wanted to make sure the height pleased me.

P1140720

The height I had to be to get this shot did not please me, but I just had to follow the progress from above. The fireplace on the porch will have a raised hearth, so although the fireboxes are back to back they aren’t completely symmetrical.

From this view, you can see the ash drop and the tunnel where the gas starter will run.

While all this was going on, the low voltage guys were steadily stringing up boxes for phone, computers, tv, internet, alarm, smoke and carbon detectors, etc, and the electricians were working on their punch list from the inspection. A sheet rock installer was measuring and taking notes to prepare a bid, and a foam installer and a cabinet maker were finalizing their bids.P1140724

The house looks so peaceful sitting there. It’s hard to imagine what a hive of activity it was today.